Desk archive

LNG

Cedar LNG Passed 70 Percent Complete. First Cargo Is Still Late 2028

Cedar LNG's October 21 fall newsletter said overall construction is now more than 70 percent complete, with Kitimat site work and floating LNG fabrication in South Korea advancing. The project still targets late 2028 for the world's first Indigenous majority-owned LNG plant. That is progress reporting, not first LNG.

Oct 22, 2026
Pipelines

Canadian Utilities Broke Ground on Yellowhead. Service Is Still Late 2027

Canadian Utilities said October 13 it held a groundbreaking on the $2.9 billion Yellowhead gas pipeline from Peers to Fort Saskatchewan. The 235-kilometre line is fully contracted for 1.1 billion cubic feet a day. AUC approval came in July. That is construction start, not a 2026 volume add.

Oct 21, 2026
Markets

Pembina's West Coast HOA Definitives Are Due This Month. October 1 Is the Next Clock

Pembina's July 2 heads of agreement contemplates definitive agreements targeted for September 2026 on the proposed West Coast crude pipeline. Pembina would hold 10 percent at construction with up to another 10 percent at commercial operation. Chief legal officer Sarah Schwann cited an October 1 Building Canada Act designation milestone.

Sep 8, 2026
Pipelines

Pembina's West Coast HOA Points at September Definitives. FID Is Still Later

On July 2 Pembina signed a non-binding heads of agreement to join a proposed one million barrel a day Alberta-to-West Coast oil corridor with Ottawa, Alberta, and Trans Mountain Corporation. Pembina's economic interest starts at 10 percent. Definitive agreements are targeted for September 2026.