East Daley Just Raised Northeast Gas Supply. Data Centers Are the Reason, With a Filter
Marcellus and Utica production is now seen rising from 37.2 Bcf per day in 2026 to about 43.3 by 2030. East Daley is tracking more than 110 Northeast data center projects. The headline gas burn is 10.7 Bcf a day. The risked number is 2.2.