Tuesday, October 27, 2026
HH: $3.03 +0.3%

NPI

Northland Power

TSX · Offshore wind, thermal, renewables · 5 desk pieces in archive

Promote this name

Promote package is $49 for 30 days. Membership is $49 for the year if you also want Trends. A prompted news release is $99.

Promote NPI

Desk archive

International

Northland Filled Out Hai Long's 73 Turbines. Final Permits Are Still 2027

Northland said October 15 all 73 turbines at the 1.0 GW Hai Long offshore wind project in the Taiwan Strait are installed and generating power. Costs remain on budget. Final permitting approvals are still expected in the first half of 2027. That is mechanical completion momentum, not final COD.

Oct 22, 2026
Markets

Northland Set November 12 for Q3 Results. The Call Is Not Baltic Power COD

Northland Power said October 16 it will release third-quarter 2026 results after the close Thursday, November 12, with an earnings call November 13 at 9:00 a.m. Eastern. The GlobeNewswire note is dated October 16. That is the calendar. It is not commercial operations at Baltic Power and not Hai Long final permitting.

Oct 22, 2026
International

Northland Installed All 76 Baltic Turbines. That Is Not COD

Northland said Wednesday all 76 turbines are in at the 1.1 GW Baltic Power project in Poland with ORLEN. More than one-third are generating. First power was July 2026. Commercial operations are still later in 2026. That is install complete, not COD.

Oct 8, 2026
International

Northland Put First Baltic Power Electrons on Poland's Grid. COD Is Still Second Half

On August 12 Northland said Baltic Power, 1.1 gigawatts in Poland, delivered first offshore-wind power to the national grid. 61 of 76 turbines were installed and 15 were generating. Commercial operations are still aimed at the second half of 2026. Second-quarter adjusted EBITDA was $259 million. The quarter printed a $54 million net loss.

Aug 27, 2026

Back to listed book row · Today's desk file

Markets
-0.9%