Monday, November 16, 2026
Gas: $1.31/LPower: 2.7¢/kWhHH: $3.23 -3.3%
Power September 12, 2026

Hydro One Asked the OEB for the North Shore Link. The Line Is $1.3 Billion

On September 11 Hydro One Networks and Hydro One Sault Ste. Marie filed a joint leave-to-construct application for a new 230-kilovolt line from Mississagi Transformer Station near Wharncliffe to Third Line TS in Sault Ste. Marie. In-service is targeted for 2029.

All For Energy
Energy Market Analysis

This is an application. Steel is still three years out

Hydro One Limited (TSX: H) said September 11 that Hydro One Networks Inc. and Hydro One Sault Ste. Marie LP filed a joint leave-to-construct application with the Ontario Energy Board for the North Shore Link. The filing is required under Section 92 of the Ontario Energy Board Act, 1998 before a transmitter can build or reinforce the system.

The proposed line is a new 230-kilovolt connection from Mississagi Transformer Station near Wharncliffe to the HOSSM-owned Third Line station in Sault Ste. Marie. Hydro One would upgrade Mississagi TS and expand nearby Algoma TS. HOSSM would handle upgrades at Third Line. Hydro One put the investment at $1.3 billion and said the line is expected in service in 2029.

Nine potential First Nation partners would have the chance to invest in a 50 percent equity stake in the transmission-line component under Hydro One's First Nation Equity Partnership Model. Ryan Docherty, executive vice president of capital portfolio delivery, said the project is one of a series of investments the company will advance with First Nations as Ontario demand rises and existing kit ages.

Hydro One reported $39.7 billion of assets at December 31, 2025, and $9 billion of 2025 revenue. It invested $3.4 billion in its networks last year. This filing does not add megawatts. It asks the regulator for permission to build a wire.

Related Articles

Power

Northland Posted Q3 Adjusted EBITDA of $280 Million With Jurassic BESS in Service and Net Income of $201 Million. That Is Not Baltic COD Certification

Northland Power Inc. said November 12, 2026 on GlobeNewswire it earned third-quarter 2026 revenue from energy sales of $565 million, adjusted EBITDA of $280 million, up 9 percent year over year, and net income of $201 million after a $456 million loss in the prior-year quarter. Free cash flow per share was $0.06. The release cites commercial operations on the 80 megawatt Jurassic battery project in Alberta ahead of schedule and under budget, full turbine installation at Hai Long in Taiwan, and commissioning progress at the 1.1 gigawatt Baltic Power project in Poland. Management reaffirmed 2026 full-year guidance. This is listed power quarterly results on the after-close wire. It is not AESO pool price at one hour and not a dividend record date without the Q3 table.

Nov 13, 2026
Power

Canadian Utilities Posted Q3 Adjusted Earnings of $117 Million With $653 Million of Capex and Yellowhead Pipeline Construction Under Way. That Is Not Emera Closing Day

Canadian Utilities Limited said November 6 on CNW it earned third-quarter 2026 adjusted earnings of $117 million, or $0.43 per share, up from $108 million a year earlier. IFRS earnings attributable to equity owners were $94 million, or $0.28 per Class A and Class B share. The company invested $653 million of capital expenditures, with Yellowhead Pipeline construction commenced after AUC facility approval July 17. This is regulated utility quarterly results on the wire. It is not the ATCO parent structures backlog alone and not merger completion.

Nov 10, 2026
Power

ATCO Posted $112 Million Adjusted Q3 Earnings at $1.00 per Share With Structures Backlog Awards. That Is Not Merger Closing Day

ATCO Ltd. said November 6 on the CNW release it earned adjusted earnings of $112 million or $1.00 per share in the third quarter of 2026 versus $103 million or $0.92 per share a year earlier. IFRS earnings attributable to Class I and II shares were $83 million or $0.74 per share versus $85 million or $0.76 per share. The release recaps the October 6, 2026 Canadian Utilities and Emera merger-of-equals plan and cites Canadian Utilities investing $653 million of quarterly capex with Yellowhead Pipeline construction underway. ATCO Structures highlights include a $179 million Perpetua dormitory lodge contract and modular awards in Canada, the United States, and Australia. This is parent consolidated quarterly results on the wire. It is not Emera transaction completion and not a Yellowhead in-service certificate.

Nov 7, 2026
Markets
-0.2%