Woodfibre Was 65 Percent Built in June. Enbridge Still Holds 30 Percent of a 2027 Startup

Woodfibre LNG CEO Luke Schauerte said June 12 the Squamish plant was 65 percent complete after the powerhouse module arrived, with startup targeted for 2027. Enbridge holds 30 percent. Pacific Energy holds 70 percent. Nameplate is about 2.1 million tonnes a year.

All For Energy
Energy Market Analysis

The last completion print is June. First cargo is still a 2027 file

Woodfibre LNG, the 2.1 million-tonne-a-year export plant under construction near Squamish, B.C., was 65 percent complete as of June 12, according to chief executive Luke Schauerte speaking to The Canadian Press at the Global Energy Show. The powerhouse module had just arrived. It was the 16th module on site. Schauerte said the 2026 job is connecting components, with startup targeted for 2027.

The project is owned 70 percent by Pacific Energy Corporation, a unit of Singapore's RGE, and 30 percent by Enbridge Inc. (TSX: ENB, NYSE: ENB). That 30 percent is the listed-issuer hook. Enbridge has not posted a newer completion percentage since that June interview. A March construction note had the job near 60 percent after pretreatment and process-utility modules landed.

Woodfibre is meant to run on BC Hydro power and is accessible only by water. Nameplate is about one-seventh of LNG Canada's first phase. Cedar, the Haisla-Pembina floating plant at Kitimat, is still a late-2028 story at 3.75 million tonnes. Woodfibre is the nearer second dock if the 2027 startup holds.

This is steel in Howe Sound. It is not a 2026 Kitimat cargo count.

Related Articles

LNG

LNG Canada Took Phase 2 FID to Double Kitimat to 28 Mtpa With Up to 4,000 Construction Jobs. That Is Not Train 1 Export Certificate

LNG Canada Development Inc. said September 28, 2026 on CNW that joint venture participants Shell, PETRONAS, PetroChina, Mitsubishi Corporation, and KOGAS approved final investment decision on Phase 2 in Kitimat on Haisla Nation territory. The expansion adds two trains within the existing footprint, lifts capacity from 14 to 28 million tonnes per annum, and includes another storage tank and berth with Coastal GasLink compressor expansion led by LNG Canada as execution manager. Peak construction could host up to 4,000 new Kitimat jobs. This is liquefaction expansion FID on the issuer newswire. It is not Cedar FLNG mechanical completion and not first Phase 2 LNG cargo.

Nov 12, 2026
LNG

Pembina Said Cedar LNG Float Construction Was Over 77 Percent Complete at Q3 With Substation Work Starting at Kitimat. That Is Not First Cargo

In its November 5 Business Wire third-quarter 2026 release Pembina Pipeline Corporation said construction of the Cedar LNG floating vessel was more than 77 percent complete at quarter end, with electrical substation construction on the marine terminal recently commenced after Cedar Pipeline mechanical completion earlier in 2026. The company expects 2026 to be the largest single capital investment year for Cedar, with focus on the vessel, marine terminal mooring foundations, and transmission line installation. This is Kitimat FLNG construction status through a listed midstream partner. It is not LNG Canada phase one first export and not Woodfibre FID.

Nov 9, 2026
LNG

Coastal GasLink Phase 2 Expansion Reached FID at Up to 4.5 Bcf/d After LNG Canada’s Decision. That Is Not First Cargo From Kitimat

TC Energy said November 5 LNG Canada and its joint venture participants approved Coastal GasLink Phase 2 Expansion, adding about 2.0 Bcf per day of firm capacity to roughly 4.5 Bcf per day on a project estimated at $4.9 billion with construction expected to start in early 2027. The GlobeNewswire release states LNG Canada will lead execution and Coastal GasLink LP secured project-level financing of up to $3.3 billion. This is a sanctioned pipe expansion tied to Kitimat LNG feedgas. It is not a liquefaction train startup certificate and not Cedar FID.