LNG November 9, 2026

Pembina Said Cedar LNG Float Construction Was Over 77 Percent Complete at Q3 With Substation Work Starting at Kitimat. That Is Not First Cargo

In its November 5 Business Wire third-quarter 2026 release Pembina Pipeline Corporation said construction of the Cedar LNG floating vessel was more than 77 percent complete at quarter end, with electrical substation construction on the marine terminal recently commenced after Cedar Pipeline mechanical completion earlier in 2026. The company expects 2026 to be the largest single capital investment year for Cedar, with focus on the vessel, marine terminal mooring foundations, and transmission line installation. This is Kitimat FLNG construction status through a listed midstream partner. It is not LNG Canada phase one first export and not Woodfibre FID.

All For Energy
Energy Market Analysis
Coastal industrial terminal and marine horizon
Picsum

FLNG hull progress on the Q3 disclosure line

Pembina Pipeline Corporation (TSX: PPL) (NYSE: PBA) embedded a Cedar LNG construction update in its third-quarter 2026 results release dated November 5, 2026 on Business Wire. Pembina holds a 49.9 percent interest in Cedar LNG alongside the Haisla Nation majority stake.

At the end of the third quarter of 2026, construction of the Cedar LNG floating liquefaction vessel was over 77 percent complete. Following mechanical completion of the Cedar Pipeline earlier in the year, construction of the electrical substation on the marine terminal site had recently commenced.

Pembina stated 2026 is expected to be the largest single capital investment year for the project. The remainder of 2026 is focused on progressing construction of the floating LNG vessel, completing the substation and mooring foundations at the marine terminal, and commencing installation of the transmission line.

The parent release also reported consolidated third-quarter adjusted EBITDA of $1.128 billion and updated 2026 guidance, but this note is limited to the Cedar LNG construction paragraph in that filing.

This is project construction status from issuer quarterly disclosure. It is not a Coastal GasLink Phase 2 FID restatement and not a Kitimat export cargo tally.

Related Articles

LNG

LNG Canada Took Phase 2 FID to Double Kitimat to 28 Mtpa With Up to 4,000 Construction Jobs. That Is Not Train 1 Export Certificate

LNG Canada Development Inc. said September 28, 2026 on CNW that joint venture participants Shell, PETRONAS, PetroChina, Mitsubishi Corporation, and KOGAS approved final investment decision on Phase 2 in Kitimat on Haisla Nation territory. The expansion adds two trains within the existing footprint, lifts capacity from 14 to 28 million tonnes per annum, and includes another storage tank and berth with Coastal GasLink compressor expansion led by LNG Canada as execution manager. Peak construction could host up to 4,000 new Kitimat jobs. This is liquefaction expansion FID on the issuer newswire. It is not Cedar FLNG mechanical completion and not first Phase 2 LNG cargo.

Nov 12, 2026
LNG

Coastal GasLink Phase 2 Expansion Reached FID at Up to 4.5 Bcf/d After LNG Canada’s Decision. That Is Not First Cargo From Kitimat

TC Energy said November 5 LNG Canada and its joint venture participants approved Coastal GasLink Phase 2 Expansion, adding about 2.0 Bcf per day of firm capacity to roughly 4.5 Bcf per day on a project estimated at $4.9 billion with construction expected to start in early 2027. The GlobeNewswire release states LNG Canada will lead execution and Coastal GasLink LP secured project-level financing of up to $3.3 billion. This is a sanctioned pipe expansion tied to Kitimat LNG feedgas. It is not a liquefaction train startup certificate and not Cedar FID.

Nov 5, 2026
LNG

AltaGas Posted Record Q3 LPG Exports at 147,176 Bbl/d. Utilities Loss Is Not REEF FID

AltaGas Ltd. said October 29 it earned third-quarter 2026 normalized EBITDA of $389 million and normalized EPS of $0.29, with midstream growth led by liquid petroleum gas cargoes to Asia and Pipestone II. The CNW release cites 147,176 barrels per day on 24 VLGCs and REEF Phase I about 90 percent complete. This is filed quarterly results. It is not an AECO daily cash print and not a final REEF investment decision.

Oct 29, 2026
Markets
-0.2%