LNG November 12, 2026

LNG Canada Took Phase 2 FID to Double Kitimat to 28 Mtpa With Up to 4,000 Construction Jobs. That Is Not Train 1 Export Certificate

LNG Canada Development Inc. said September 28, 2026 on CNW that joint venture participants Shell, PETRONAS, PetroChina, Mitsubishi Corporation, and KOGAS approved final investment decision on Phase 2 in Kitimat on Haisla Nation territory. The expansion adds two trains within the existing footprint, lifts capacity from 14 to 28 million tonnes per annum, and includes another storage tank and berth with Coastal GasLink compressor expansion led by LNG Canada as execution manager. Peak construction could host up to 4,000 new Kitimat jobs. This is liquefaction expansion FID on the issuer newswire. It is not Cedar FLNG mechanical completion and not first Phase 2 LNG cargo.

All For Energy
Energy Market Analysis
Energy infrastructure and industrial skyline at dusk
Unsplash

FID on trains, not molecules sailing today

LNG Canada Development Inc. announced September 28, 2026 in a CNW release that joint venture participants approved final investment decision on the Phase 2 expansion at the Kitimat liquefied natural gas export facility on the traditional territory of the Haisla Nation.

Participants are Shell Canada Energy, PETRONAS through North Montney LNG, PetroChina Canada, Mitsubishi Corporation through Diamond LNG Canada, and KOGAS Canada. Phase 2 adds two LNG processing trains within the existing site, increasing total production capacity from 14 million tonnes per annum to 28 million tonnes per annum. The scope includes an additional LNG storage tank, condensate tank, loading berth, and expanded utility and process systems.

LNG Canada stated it entered commercial agreements to act as execution manager and work with Coastal GasLink to expand the existing 670-kilometre pipeline capacity through construction of five new compressor stations. Phase 1 infrastructure was engineered from the outset to support a four-train facility, per the release.

At peak construction, Phase 2 is expected to host up to 4,000 new construction jobs in Kitimat, alongside roughly 2,100 jobs to build new compressor stations along Coastal GasLink. When complete, LNG Canada expects approximately 90 additional full-time roles and 150 contractor positions beyond its existing Kitimat operating workforce of more than 400 permanent full-time jobs.

Phase 1 commenced shipping operations June 30, 2025 with two trains and approximately 14 million tonnes per annum capacity under a 40-year export licence, per the same CNW notice.

TC Energy's November 5, 2026 third-quarter release separately confirmed Coastal GasLink Phase 2 proceeds following this FID. Pembina's November 5 release covered Cedar LNG construction progress. This note is the September 28 LNG Canada issuer release on liquefaction expansion. It is not Woodfibre FID and not a Coastal GasLink in-service certificate.

Related Articles

LNG

Pembina Said Cedar LNG Float Construction Was Over 77 Percent Complete at Q3 With Substation Work Starting at Kitimat. That Is Not First Cargo

In its November 5 Business Wire third-quarter 2026 release Pembina Pipeline Corporation said construction of the Cedar LNG floating vessel was more than 77 percent complete at quarter end, with electrical substation construction on the marine terminal recently commenced after Cedar Pipeline mechanical completion earlier in 2026. The company expects 2026 to be the largest single capital investment year for Cedar, with focus on the vessel, marine terminal mooring foundations, and transmission line installation. This is Kitimat FLNG construction status through a listed midstream partner. It is not LNG Canada phase one first export and not Woodfibre FID.

Nov 9, 2026
LNG

Coastal GasLink Phase 2 Expansion Reached FID at Up to 4.5 Bcf/d After LNG Canada’s Decision. That Is Not First Cargo From Kitimat

TC Energy said November 5 LNG Canada and its joint venture participants approved Coastal GasLink Phase 2 Expansion, adding about 2.0 Bcf per day of firm capacity to roughly 4.5 Bcf per day on a project estimated at $4.9 billion with construction expected to start in early 2027. The GlobeNewswire release states LNG Canada will lead execution and Coastal GasLink LP secured project-level financing of up to $3.3 billion. This is a sanctioned pipe expansion tied to Kitimat LNG feedgas. It is not a liquefaction train startup certificate and not Cedar FID.

Nov 5, 2026
LNG

AltaGas Posted Record Q3 LPG Exports at 147,176 Bbl/d. Utilities Loss Is Not REEF FID

AltaGas Ltd. said October 29 it earned third-quarter 2026 normalized EBITDA of $389 million and normalized EPS of $0.29, with midstream growth led by liquid petroleum gas cargoes to Asia and Pipestone II. The CNW release cites 147,176 barrels per day on 24 VLGCs and REEF Phase I about 90 percent complete. This is filed quarterly results. It is not an AECO daily cash print and not a final REEF investment decision.