NexGen's September Investor Day Put First Ore in Q3 2030. Rook I Is Under Construction
NexGen hosted its 2026 Investor Day on September 1 with a pre-recorded construction plan for Rook I. Management targeted first ore in the third quarter of 2030, freeze plants in Q1 2027, and main shaft sinking in 2028. The project received final federal approval in March.