Regulated capex and Yellowhead construction on the CNW filing
Canadian Utilities Limited (TSX: CU) released third-quarter 2026 results November 6, 2026 on CNW. Adjusted earnings were $117 million or $0.43 per share compared with $108 million or $0.40 per share in the third quarter of 2025.
Earnings attributable to equity owners under IFRS were $94 million or $0.28 per Class A and Class B share versus $100 million or $0.29 per Class A and Class B share in the prior-year quarter.
The release states the company invested $653 million of capital expenditures in the quarter, of which about 95 percent was invested in regulated utilities in ATCO Energy Systems and ATCO Australia. It describes the Yellowhead Pipeline Project as roughly 235 kilometres of high-pressure natural gas pipeline with projected spend estimated at $2.9 billion, notes Alberta Utilities Commission approval of the facility application on July 17, 2026, and states construction has commenced with the pipeline fully contracted with customers.
On ATCO Australia, the release cites $29 million of adjusted earnings in the third quarter of 2026, an increase of $2 million compared with the same period in 2025, driven by the impact of inflation indexing on rate base.
The release references an October 6, 2026 agreement among ATCO Ltd., Canadian Utilities, and Emera Incorporated to combine Canadian Utilities and Emera in a merger of equals, subject to conditions and approvals, with expected completion in the third or fourth quarter of 2027, and notes an October 8, 2026 declaration of a fourth-quarter dividend of 46.23 cents per share.
This note is issuer utility quarterly results from the CNW release. It is not Fortis Alberta rate decision text alone and not a Tilbury LNG cargo.